Major Milestone – Finished the Fuel Tanks – Is it Possible?

Got a bit of catching up to do here and I don’t have a lot of pictures so I’ll just get with it.

Since last update, I completed closing the right side tank by pro sealing and riveting the aft tank baffle. Right side went much like the left but I think I was a little more tidy with proseal along the skin to baffle rivet line so it didn’t squeeze out through all of the rivet holes nearly as bad.  Also, I only had time to do the Z-Bracket pop rivets so I let the skin-baffle rivets set up overnight under 100% clecos and riveted the next day.  That method is so much cleaner.

Now the final tasks for closing the tank are to proseal and install the fuel level sender and to install the various fittings for the fuel pick up, tank drain, etc.  I did the senders first.  That involves putting a thin smear of proseal on the tank’s mating surface then maneuvering the float wire and mechanism into the tank.  Then slowly tightening down the 5 cap head screws to evenly squeeze the proseal for what is essentially a “cured in place” gasket.

Last item to close the tanks and get them ready for leak testing is to install the fittings.  This can be counted as a lesson learned too late but it turned out ok in the end.  As I was preparing to install the tank drain fitting, I noticed that about 3/4 of the hole was blocked by proseal.  This would have been much easier to clear out from inside the tank before closing but it was too late for that.  So I ground down a razor blade so it was very narrow so it would fit into the drain hole. I then carefully carved away the proseal while being careful to extract the pieces so they wouldn’t become FOD in the tank.  It worked fine just took longer than it should have.

So finally, one of the days I’ve been apprehensive about since starting this build.  Yesterday was time to leak test the completed tanks.  The setup looks something like this, with a balloon on the fuel pickup fitting (secured with a zip tie) and a hose with a Schrader valve to allow for “pressurizing” the tank.  As long as the balloon is inflated, you know that there’s positive pressure in the tank so any leak should result in air coming out, and bubbles in soapy water.

IMG 20200606 140343 copy 

In an ideal world, the test fittings themselves wouldn’t leak so you could observe that the balloon doesn’t deflate.  Bun in my case, there was a leak around the balloon itself so I simply sprayed the entire tank with soapy water to look for bubbles.  I paid special attention to the troublesome areas such as the corners where three pieces of aluminum come together, the fuel sender, and everything having to do with the baffle.

IMG 20200606 135952

In the end, the only leak I found was around the fuel cap on the right wing.  The fuel caps are adjustable so I can adjust it a little tighter but in reality, that’s at the tippy top of the tank so I really doubt it will be an issue even if I didn’t.

IMG 20200606 142327

I couldn’t be more excited to be past this milestone.  I will probably perform this test once more before hanging the tanks on the wing just to be sure but at least now I know they’re not leaking like a sieve.  

Closed the left tank

Alright, for better or for worse, the left fuel tank is sealed. I’ve gotten back into the habit of going to the workshop after the kids go to bed instead of watching re-runs of Forged in Fire so I’ve gotten some time in over the last couple of weeks.

After preliminary leak test, I pro sealed up the tank skins and the ribs and slid the “baffle”, or aft bulkhead, into place and 100% clecoed then riveted

.IMG 20200524 235023

And… in full disclosure, I was an idiot and left off the most inboard Z-Bracket and drove a handful of rivets. I know, I know.

IMG 20200524 235029

So I opted to let the proseal cure before trying to remove those rivets and properly install the bracket the next night.  So after curing for 24 hours, I removed the rivets and fixed the bracket.

So left tank closed.  I’ve ordered some loctite from the aviation section of Amazon that I need to finish installing the fuel fittings.  While I wait for that to arrive, I’ll probably switch over to the right side.

 

DRDT Laser Sight

I had a small Christmas break project that may be worth reporting.

It has always driven me a bit crazy using the DRDT-2 on large pieces. I had a tendency to fish around trying to get the die to mate with the rivet hole, putting small scratches on the piece. So I decided to make a laser sight.

I think there are various ways to accomplish this task, this is what I chose:

Step 1: Acquire Laser. In this case, a Drill Press laser sight from Amazon for $40.

Screen Shot 2016 01 01 at 3 40 12 PM

Step 2: Epoxy rare earth magnets to the case of the laser. I used rare earth because they’re thinner. This thing already sticks down into the neck space of the DRDT enough.

IMG 0398

Step 3: Attach the laser to the DRDT and adjust. The laser is fully adjustable but I think the easiest thing to do is get it roughly adjusted then just move it around slightly until the X hits the dimple die.

IMG 0399

As I said above, it does stick down into the open neck of the DRDT a little, maybe an inch or so. It may not be usable for anything other than large flat pieces but if I want to remove it, I’ll just take it off and the magnets will stick it to the top of the DRDT where I store some Dies, etc.

After I ordered the laser sight, I saw something online that gave me another idea for a solution that may be better. You could just use a regular office laser pointer with a magnetic helping hand (the kind they use in electronics and stuff to help solder). The only trick there would be devising something to keep the button pushed but I’m sure something could be worked out. That would have the advantage of not sticking down into the free space. And since the die doesn’t move up or down, a single laser dot would do the job just fine.

I’ve got some big skins to dimple this weekend so I’ll report back how it does.

Elevator

I’ve finished all of the elevator except for wiring the trim tab servo. I had to order a crimper and some Molex pins that were missing from my kit.

IMG 0057

The main thing that I had to rework was the trim tab hinge. I attached both of the halves of the piano hinge as per the instructions but the half on the elevator spar was warped.
IMG 0058
I ordered replacement parts, drilled out the bad piece (about 25 rivets) and redid that hinge. This time, I kept the hinge assembled while I positioned and drilled the hinge. This kept the piece from warping.
IMG 0063

Anther thing worth noting is that I built a tool to make rolling of the leading edge easier. This idea was something I got from a post on =VAF= and is simply a closet rod with a 7/8 inch socket epoxied into the end. This lets you use a socket wrench to do the turning instead of vise grips on a broomstick. I made two: one long one with a socket on both ends, and one short one with one socket for use on the short section at the end. By my counting, this is the last rolled edge on the plane so I probably won’t use it again but it was well worth the effort to build.

IMG 0055IMG 0056

I’m Still Working on it

I know it’s been 12 months to the week since I published anything here but I am still working on the build. I’ve had to prioritize things a bit. Given much less time available to build, I’ve been spending what time I do have in the workshop instead of on the computer writing about it. I would like to pick the blogging back up so I intend to get something of a catchup post out at some point during the holidays.

In general, I’ve continued to work on the empennage kit, completed the V Stab, H Stab, Rudder and am just wrapping up work on the elevator and trim tab assembly. I will be starting the tail cone (Chapter 10) this week.

After that, I will return to the wings and finish the fuel tanks and the rest of the wing construction before biting the bullet to buy the Fuselage kit.

Rudder

Section 7 is the rudder. I started working on the rudder over this long Thanksgiving weekend and have gotten a good number of hours in. There’s a surprisingly large number of parts in the rudder assembly and the first several steps involve separating parts and deburring.

I do have one small tip when it comes to cutting the stiffeners. The plans have you draw a cut line on each stiffener then trim along the line. Below you can see the cut line on one of the stiffeners.
IMG 3862

I nested a 1×2 piece of scrap wood in the bend of the stiffener and carefully cut the first stiffener with the band saw. This resulted in a cut in the 1×2 that served to guide the band saw blade for each subsequent stiffener I cut. I just had to align the end of the stiffener with the end of the 1×2. Since there are Right and Left hand stiffeners, I had a cut on each side of the 1×2 that you can see below. This made quick work of what is normally a tedious job.
IMG 3864

After getting all of the parts cut and deburred, It’s time rivet the hinge doublers to the spar
IMG 3875

and assemble the rudder skeleton and skin for some match drilling.
IMG 3877

IMG 3876

IMG 3878

IMG 3874

IMG 3873

After some match drilling, including the trailing edge, It is time to disassemble and debur everything. More on that tomorrow.

Vertical Stabilizer

Completed the Vertical Stabilizer last weekend. It’s exciting to be working aluminum again. I opted to skip (backwards) in the plans rather than dive back into proseal and fuel tanks right off the bat. Since I have the Empenage kit I opted to get started on the vertical stabilizer. Unfortunately, I neglected to take many pictures. I guess that’s a habit to get back into also.

Here is Ashley holding up the clecoed stabilizer skeleton after the first day of building in over 6 months.
IMG 3833

and fast forward to the end product, the completed vertical stabilizer
IMG 3855IMG 3854

Another note to get out of the way, I have opted not to prime the pieces going forward. This is an item that receives quite a bit of debate but the bottom line is that I live in mostly arid climate and there is little real evidence that I’ve seen that shows corrosion on 2024-T3 aluminum. There are thousands of Cessna aircraft out there built in the 50’s and 60’s with 2024 that were not primed and are flying today. I started the build not knowing for sure which way I would go so I opted for the “may as well prime because I can decide not to later” approach. As I went through the build, I found how much additional time priming took so now is the time that I decide not to.

Move complete and new workshop ready

Well, It’s been quite a while since I’ve made an forward progress on airplane building. Here is a big part of the reason. Ashley and I decided to sell our house and move to the Burleson area. We wanted a place large enough for a little boy to run around and get into trouble without having to cross city streets. I, of course, also wanted larger workshop space.

So……
IMG 3282

30×40 workshop / Airplane factory
IMG 3381

and, after a ton of help from Dad and a successful move…
IMG 3660

Since I can’t hang stuff on the walls here very easily, I had some fixtures to build. So that took a good bit of time but now I’ve got a great deal of storage and workbench space and I’m ready to start working aluminum again.

Fuel Tanks 5

Been quite a while since I did any productive work on the wing kit after working on Emp inventory, dealing with a flu bug, etc, etc. I know, excuses, excuses…

Did a little more work on the left fuel tank. Last weekend I sealed and riveted the outboard end rib, and the inboard fwd half rib.

Mom and Dad are in town for a day so today we prosealed the J-stiffener and the tank attach bracket. We’ll drive the rivets tomorrow.

Tank with the J-stiffener and bracket clecoed in place to set up overnight.
IMG 3170

the outboard end rib riveted and sealed
IMG 3171

Fuel tank attach bracket
IMG 3172

Sometimes the proseal plays nicely and you get a nice looking sealed surface with nice squeeze out…
IMG 3174

…and some times the proseal gets angry at you…
IMG 3173

Empennage Inventory Complete

Ashley and I finished inventoring the Emp kit today. The only thing missing was 6 molex pins and a few AN470AD3-3.5 rivets. Normally I wouldn’t worry about the rivets but I don’t have any of these so I’ll ask Van’s to send them.

Here’s a picture of the unopened box. I’ll get some pictures of the stuff all stored away in the garage soon.

IMG 3122